East Greenwich High School
The project involves an occupied, phased renovation of the existing EGHS facility, which will include:
-
A new addition to support the Life Skills program, featuring an apartment, vocational/technical lab, PT and OT spaces, and additional classrooms.
-
Renovation of locker rooms, team rooms, and athletic storage areas.
-
Reconfiguration of the Upper Gym to include a basketball court and new Fitness/Adaptive PE space.
-
Thermal comfort, acoustic, and code upgrades to the Auditorium.
-
Renovation and reconfiguration of the Arts Suite, including Ceramics, Photography, and Fashion classrooms.
-
General Mechanical, Electrical, Plumbing, and Code Upgrades.
For more information on Design and Construction Logistics, please click the LEARN MORE button below.
Activities this week: ( August 31 – September 04, 2026)
- Addition:
- Continued to complete pulling wire to electrical boxes.
- Continue installing windows.
- Continue to final terminate seams and set sleepers.
- Continue the overhead MEP on both levels.
- Complete inwall inspections
- Begin to board, tape, and sand walls.
- Auditorium:
- Continue electrical rough and routing.
- Continue to drop ducts into interior.
- Locker Room:
- Continue installing CMU walls.
- Continue MEP in-wall and overhead.
- Mechanical Room
- Continue exterior site work for RIE inspection.
- Continue interior conduit, ground, primaries, and connections work.
- Complete installing and tying in boiler piping.
- Begin powering connections to boilers and pumps.
- Continue installing control wiring to equipment.
- Upper Gym
- Continue overhead MEP work.
- Complete framing divider wall.
- Begin in-wall rough at the divider wall.
- Exterior Site:
- Begin underground utility work.
- Complete relocating storage areas.
Activities for next week: ( September 07 – 11, 2026)
- Addition:
- Continue the overhead MEP both levels.
- Complete installing windows.
- Continue installing roof top unit power connections.
- Continue to board, tape, and sand walls.
- Continue to complete final terminate seams and set sleepers.
- Auditorium:
- Continue dropping duct into the interior.
- Begin to complete relocating conduits below the ducts.
- Locker Room:
- Continue installing CMU walls.
- Continue MEP in-wall and overhead.
- Begin installing lintel at brick openings in Health Classroom.
- Mechanical Room
- Continue RIE transformer work.
- Continue powering connections to boilers and pumps.
- Begin to install water and gas connections to boilers.
- Continue to complete installing control wiring to equipment.
- Upper Gym:
- Continue overhead ductwork, pipe, and electrical.
- Continue to sawcut exterior openings.
- Begin to complete install of lintels at the openings for the windows.
- Exterior Site:
- Continue underground utility work.
- Begin prep for bus loop.
- Begin to complete repairing the sprinkler head/line.
- Begin to tie into the drainage and backwater valve.